求翻译:By the date of August 07, the construction at 0# platform has been finished 5 bored piles of Φ1.5m, and 7 bored piles of Φ2.2m at 1# pier. Besides, the pile cab of 1# pier has also been finished. Accumulated amount of full bridge reinforcements has been reached to 260.88t, which takes 11.5% of the contract quantities. 是什么意思?

待解决 悬赏分:1 - 离问题结束还有
By the date of August 07, the construction at 0# platform has been finished 5 bored piles of Φ1.5m, and 7 bored piles of Φ2.2m at 1# pier. Besides, the pile cab of 1# pier has also been finished. Accumulated amount of full bridge reinforcements has been reached to 260.88t, which takes 11.5% of the contract quantities.
问题补充:

  • 匿名
2013-05-23 12:21:38
正在翻译,请等待...
  • 匿名
2013-05-23 12:23:18
正在翻译,请等待...
  • 匿名
2013-05-23 12:24:58
不迟于日期8月07日,建筑在0#平台完成了5乏味堆Φ1.5m和7乏味堆Φ2.2m在1#码头。 其外,也完成了1#码头堆小室。 积累相当数量充分的桥梁增强被到达了对260.88t,采取11.5%合同数量。 并且2404.3m3合同工作的混凝土作为15.4%。 而且,在右岸完成了土堤挖掘10000m
  • 匿名
2013-05-23 12:26:38
8 月 07 日期,由 5 钻孔灌注的桩的 Φ1.5m 和 Φ2.2m 1 # 码头 7 钻孔灌注的桩已完成 0 # 平台建设。此外,亦已完成 1 号墩桩司机室。全桥增援部队累计的金额已达 260.88t,占合同数量的 11.5%。混凝土的 2404.3m3 15.4%的合同工程。此外,右堤土方开挖已完成的 10000m