求翻译:因发电机机组电缆沟管道与发电机设备本体管道位置不一致,导致切割处理管道:投入技术人工16人×3天=48工日,管理人员6人×3天=18工日;吊车配合50T×3天=3个台班是什么意思?

待解决 悬赏分:1 - 离问题结束还有
因发电机机组电缆沟管道与发电机设备本体管道位置不一致,导致切割处理管道:投入技术人工16人×3天=48工日,管理人员6人×3天=18工日;吊车配合50T×3天=3个台班
问题补充:

  • 匿名
2013-05-23 12:21:38
正在翻译,请等待...
  • 匿名
2013-05-23 12:23:18
Because the power generator units of cable ducts and pipes generator equipment body position do not match, resulting in cutting processing pipeline: in Technical Manual 16 X 3 days = 48 days, the management team 6 people x 3 days = 18 days; a crane with 50 T x 3 days = 3 desktop,
  • 匿名
2013-05-23 12:24:58
Because the generator unit cable trench pipeline is inconsistent with the generator set main body pipeline position, causes to cut the processing pipeline: The investment technology artificial 16 human of ×3 day =48 man-day, the administrative personnel 6 human of ×3 day =18 man-day; Crane coordinat
  • 匿名
2013-05-23 12:26:38
Generator cable trench pipelines and pipeline location generator device ontology is inconsistent, resulting in cutting processing pipeline: input technical artificial 16 = 48 shadow days X3 days, management staff, 6 = 18 shadow days X3 days; crane combined with 50Tx3 days = 3 class
  • 匿名
2013-05-23 12:28:18
正在翻译,请等待...
 
 