求翻译:estimates that its new laboratory building will cost $3 million to construct. The purchasing department issues a bid request for construction and receives four bids. The bid from Contractor A comes in at $2.7 million. The bid from Contractor B is $4.8 million; from Contractor C it is $4.9 million; and from Contractor D是什么意思?

待解决 悬赏分:1 - 离问题结束还有
estimates that its new laboratory building will cost $3 million to construct. The purchasing department issues a bid request for construction and receives four bids. The bid from Contractor A comes in at $2.7 million. The bid from Contractor B is $4.8 million; from Contractor C it is $4.9 million; and from Contractor D
问题补充:

  • 匿名
2013-05-23 12:21:38
估计新的实验室建设将耗资300万元兴建。采购部门发出施工招标要求,并接收四个竞标。从承包商的出价为270万美元。从承包商乙出价是4.8百万美元;,从承包商彗星,它是490万美元的;和承包ð是500万美元。采购部门的下一步应该是什么?
  • 匿名
2013-05-23 12:23:18
估计,其新的实验室建设费用将为300万美元兴建。 采购部门的一个问题要求投标建造和收到四份标书。 从承包商的投标的是在为270万元。 从承包商的投标B是480万美元;从承包商C是490万美元;和从承包商D是500万美元。 应该采取怎样的采购部的下一步行动?
  • 匿名
2013-05-23 12:24:58
估计它新的实验室大厦将花费$3百万对修建。 供应科发布一个出价要求建筑并且接受四个出价。 出价从承包商A进来在$2.7百万。 出价从承包商B是$4.8百万; 从承包商C它是$4.9百万; 并且从承包商D它是$5.0百万。 什么应%
  • 匿名
2013-05-23 12:26:38
估计其新的实验室建设将花费 300 万美元兴建。采购部门发出施工投标请求和接收四份标书。招投标承建商 A 进来了 270 万美元。从承建商 B 出价是 4.8 万元 ;从承建商 C 是 490 万美元 ;并从承建商 D 是 500 万美元。采购部门下一步应该是什么?