求翻译:非固定的,无明显危险因素的场所进行三级动火作业由施工作业队(班组)填写动火申请表,经项目经理批准,也可授权项目专职安全审批。是什么意思?

待解决 悬赏分:1 - 离问题结束还有
非固定的,无明显危险因素的场所进行三级动火作业由施工作业队(班组)填写动火申请表,经项目经理批准,也可授权项目专职安全审批。
问题补充:

  • 匿名
2013-05-23 12:21:38
Non-fixed, no obvious risk factors for three hot work places by the construction operations team (team) complete flare application form, approved by the project manager can also authorize the project full-time safety approval.
  • 匿名
2013-05-23 12:23:18
non-fixed, and there is no obvious risk factors for the Place 3 level by construction operations interactive fire Operations Team (team) Fill out interactive fire application form to the project approved by the manager, may also be authorized project full-time security for approval.
  • 匿名
2013-05-23 12:24:58
Non-fixed, the not obvious dangerous factor place carries on three levels to get angry the work (teams and groups) to fill in by the construction working party gets angry the request form, authorizes by project manager, also may be authorized the project specialty safe examination and approval.
  • 匿名
2013-05-23 12:26:38
Non-fixed, no obvious place for risk factors for three-level hot work by construction team (team leader) complete the fire work application form, approved by the project manager or authorized project full-time security approval.
  • 匿名
2013-05-23 12:28:18
Non-fixed, no obvious place for risk factors for three-level hot work by construction team (team leader) complete the fire work application form, approved by the project manager or authorized project full-time security approval.
 
 