求翻译:张拉完一片梁后应立即测量梁的拱度,建立该梁的上拱值档案,测量其1天、7天、30天的上拱度,并应符合设计值,否则检查原因,予以处理。是什么意思?

待解决 悬赏分:1 - 离问题结束还有
张拉完一片梁后应立即测量梁的拱度,建立该梁的上拱值档案,测量其1天、7天、30天的上拱度,并应符合设计值,否则检查原因,予以处理。
问题补充:

  • 匿名
2013-05-23 12:21:38
After a beam tension measurement immediately after the beam camber, to establish the value of the beam on the arch file, measured 1 day, 7 days, 30 days on the camber, and should be consistent with design values, or check the reasons, be addressed .
  • 匿名
2013-05-23 12:23:18
正在翻译,请等待...
  • 匿名
2013-05-23 12:24:58
Opens pulls piece of Liang Houying to survey Liang's crown immediately, establishes this Liang's camber value file, surveys its 1 days, 7 day, 30 day-long cambers, and should conform to the design value, otherwise the inspection reason, processes.
  • 匿名
2013-05-23 12:26:38
Stretch wrap up immediately after a beam measuring deflection of a beam, Arch archives on the establishment of the beam, measuring 1 day, 7 days, 30 days of camber, and should be consistent with the design value, otherwise check reasons, be addressed.
  • 匿名
2013-05-23 12:28:18
After a beam tension measurement immediately after the beam camber, to establish the value of the beam on the arch file, measured 1 day, 7 days, 30 days on the camber, and should be consistent with design values, or check the reasons, be addressed .
 
 
网站首页

湖北省互联网违法和不良信息举报平台 | 网上有害信息举报专区 | 电信诈骗举报专区 | 涉历史虚无主义有害信息举报专区 | 涉企侵权举报专区

 
关 闭